Monthly Update

Monthly Update for November 2021

During the Month of November 2021:

  • Continued MEP rough-in below-grade parking levels and completed wet utilities tie-ins.
  • Completed setting of Level 1 cold-formed steel pre-fabricated bearing wall panels and placement of Level 2 metal decking.
  • Initiated Level 2 cold-formed steel pre-fabricated bearing wall panels and placement of Level 3 metal decking.
  • Initiated Level 3 elevated post-tensioned deck concreting.

Street Use Impacts:

    • Eastbound on Northup Way reduced to 1 lane during construction hours

 

Monthly Update for October 2021

During the Month of October 2021:

    • Completed Level 1 vertical & post-tensioned concreting.
    • Continued installation of steel stairs in core shafts.
    • Continued setting of Level 1 cold-formed steel pre-fabricated bearing wall panels.
    • Continued placement of Level 2 metal decking.
    • Initiated shoring and formwork for Level 3 elevated post-tensioned deck.

Street Use Impacts:

      • Eastbound on Northup Way reduced to 1 lane during construction hours.

 

Monthly Update for September 2021

During the Month of September 2021:

  • Continued Level 1 vertical & post-tensioned deck concreting.
  • Initiated installation of steel stairs in core shafts.
  • Initiated setting of Level 1 cold-formed steel pre-fabricated bearing wall panels.
  • Initiated placement of Level 2 metal decking.

Street Use Impacts:

    • Eastbound on Northup Way reduced to 1 lane during construction hours

 

Monthly Update for August 2021

During the Month of August 2021:

    • Complete Level P1 vertical & post-tensioned concreting.
    • Complete Level L1 vertical & post-tensioned concreting.
    • Initiated offsite bearing wall fabrication.

Street Use Impacts:

      • Eastbound on Northup Way reduced to 1 lane during construction hours.

 

Monthly Update for July 2021

During the Month of July 2021:

  • Complete Level P2 vertical & post-tensioned deck concreting.
  • Continued Level P1 vertical & post-tensioned deck concreting.
  • Initiated Level 1 vertical & post-tensioned deck concreting.

Street Use Impacts:

    • Eastbound on Northup Way reduced to 1 lane during construction hours

 

Monthly Update for June 2021

During the Month of June 2021:

  • Completed structural excavation and foundation concreting.
  • Completed vertical and slab on grade concreting at Level P3.
  • Completed installation of foundation drainage system.
  • Continued below grade vertical and post-tensioned elevated deck concreting.

Street Use Impacts:

  • Eastbound on Northup Way reduced to 1 lane during construction hours.

 

Monthly Update for May 2021

During the Month of May 2021:

  • Continued structural excavation and foundation concreting.
  • Continued vertical concreting at Level P3.
  • Continued installation of the foundation drainage system.
  • Initiated slab on grade concreting at Level P3.
  • Formwork & reinforcing started for the first elevated deck on P2.

Street Use Impacts:

    • Eastbound on Northup Way reduced to 1 lane during construction hours

 

Monthly Update for April 2021

During the Month of April 2021:

  • Continued structural excavation and foundation concreting.
  • Initiated vertical concreting at Level P3.
  • Initiated installation of foundation drainage system.
  • Completed installation of modular stormwater detention vault.

Street Use Impacts:

  • Eastbound on Northup Way reduced to 1 lane during construction hours.

 

Monthly Update for March 2021

During the Month of March 2021:

  • Tower crane erected and operational.
  • Support of excavation shoring completed.
  • Initiated structural excavation and foundation concreting.
  • Initiated installation of below-grade waterproofing.
  • Continued installation of modular stormwater detention vault.

Street Use Impacts:

    • Eastbound on Northup Way reduced to 1 lane during construction hours

 

Monthly Update for February 2021

During the Month of February 2021:

  • Mass excavation to foundation grade with support of excavation shoring activities
  • Continued installation of site utilities and start of modular storm-water detention vault
  • Installation of temporary asphalt treated base construction access road
  • Form, reinforce, & pour tower crane footing in anticipation of crane erection first week of March

Street Use Impacts:

  • Mild congestion along Northup Way arterial with eastbound reduced to 1 lane during construction hours
  • Intermittent pedestrian escorting by flaggers during sidewalk closures for utility construction equipment staging

 

Monthly Update for January 2021

During the Month of January 2021:

  • Initiated support of excavation shoring pile drilling
  • Initiated trenching & installation of site perimeter utilities
  • Continued site perimeter earthwork, grading, and mass excavation activities

 

Monthly Update for December 2020

During the Month of December 2020:

  • Completed demolition of existing storage units & foundations
  • Initiated site perimeter earthwork, grading, and mass excavation
  • Initiated trenching & installation of off-site wet utilities

 

Monthly Update for November 2020

During the Month of November 2020:

 

Demolition of the existing single story storage units will begin. Once demolition is complete the Site will begin to be cleared and grubbed with tree removal.

 

Privacy Policy Decline Accept

Our website uses cookies to ensure we provide the best experience possible.  Please accept or decline the use of cookies on your machine. For more information please review our privacy policy.

Our website uses cookies to ensure we provide the best experience possible.  Please accept or decline the use of cookies on your machine. For more information please review our privacy policy.

Accept Decline Privacy Policy