11.21.2022 | Project Update
Monthly Update August 2025
During August 2025
Monthly Update for August 2025 for Holland Construction’s 616 Battery Project:
- During the Month of August:
- Concrete Column Pours, 01/13/2025, Continuous.
- Above Grade Elevated Deck Pours 05/30/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Exterior Encloser Installation 8/17/2025, Continuous.
- Street use impacts:
- 24 Hour sidewalk closure on Battery & 7th Ave.
- 24 Hour Closure of Battery and 7th Ave.

`Monthly Update for July 2025:
During July 2025:

Monthly Update for July 2025 for Holland Construction’s 616 Battery Project:
During the Month of July:
- Concrete Column Pours, 01/13/2025, Continuous.
- Above Grade Elevated Deck Pours 05/30/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Street use impacts:
- 24 Hour sidewalk closure on Battery & 7th Ave.
- 24 Hour Closure of Battery and 7th Ave.
Monthly Update for June 2025:
During June 2025:

- Concrete Column Pours, 01/13/2025, Continuous.
- Above Grade Elevated Deck Pours 05/30/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Street use impacts:
- 24 Hour sidewalk closure on Battery & 7th Ave.
- 24 Hour Closure of Battery and 7th Ave.
Monthly Update for May 2025:
During May 2025:
- Concrete Column Pours, 01/13/2025, Continuous.
- Elevated Deck Pours 02/13/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Street Use Impacts:
- 24-Hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for April 2025
During April 2025:
- Concrete Column Pours, 01/13/2025, Continuous.
- Elevated Deck Pours 02/13/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Street Use Impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for March 2025
During March 2025:
- Concrete Column Pours, 01/13/2025, Continuous.
- Elevated Deck Pours 02/13/2025, Continuous.
- Core Pours 1/21/2025, Continuous.
- Street Use Impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-hour Closure of Battery and 7th Ave.
Monthly Update for February 2025
During February 2025:
- Concrete Column Pours, 01/13/2025, Continuous.
- 1st Elevated Deck Pour scheduled for 02/13/2025, Continuous.
- Street Use Impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-hour Closure of Battery and 7th Ave.
Monthly Update for January 2025
During January 2025:
- Concrete Foundation Footings, 11/19/2024, Continuous.
- Mat Foundation Pour scheduled for 1/4/2025.
- Street Use Impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for December 2024
During December 2024:
- Mass Excavation is to be completed in Early December.
- Concrete Foundation Footings, 11/19/2024, Continuous.
- Mat Foundation Pour scheduled for 1/4/2025.
- Street use impacts:
- 24-Hour Sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for November 2024
During November 2024:
- Mass Excavation, 5/20/2024, Continuous
- Shoring, 6/3/2024, Continuous
- Starting of Tower Crane Erection, 11/09/24-11/10/24
- Starting Concrete Foundations pours 11/25/24, Continuous
- Street use impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
- 2 Day Closure of 7th and Denny Parking Lot (11/09/24-11/10/24)
Monthly Update for October 2024
During October 2024:
- Mass Excavation, 5/20/2024, Continuous
- Shoring, 6/3/2024, Continuous
- Starting of Tower Crane Foundation, Continuous
Street use impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for September 2024
During September 2024:
- Mass Excavation, 5/20/2024, Continuous
- Shoring, 6/3/2024, Continuous
- Starting of Tower Crane Foundation, Continuous
Street use impacts:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Monthly Update for August 2024
During August 2024:
- Mass Excavation, Start Date of 05/20/2024, Continuous
- Shoring, Start Date of 06/03/2024, Continuous
- Starting of Tower Crane Foundation, Continuous
Street Use Impacts for August 2024:
- 24-hour sidewalk closure on Battery & 7th Ave.
- 24-Hour Closure of Battery and 7th Ave.
Project Description:
616 Battery is a forty-five (45) story, 494’ 9” tall, Type 1A mixed-used apartment building. The Project currently includes seven (7) levels of below-grade parking with four (4) levels above grade, 260 total parking spaces, 442 residential apartment units, 579,786 GSF constructed on a site of approximately 15,451 SF, and three (3) city-dedicated streets will be included in the development on the West, East and South sides of the property bordering the building per street improvement requirements. Level 1 at street level will contain 2,571 square feet of retail space, lobby/leasing/fitness/back-of-house, and programming. The roof will be utilized for mechanical equipment and Elevator Machine Rooms. The Project shall be constructed per the 2018 International Building Code (IBC), and 2018 Washington State Energy Codes.
Schedule Information
- Demolition: N/A
- Mass Excavation: 5/20/2024
- Shoring: 6/3/2024
- Tower Crane Erection: 8/12/2024
- Anticipated Certificate of Occupancy: 2/26/2027
For questions or concerns during construction, please contact: Tyler Parker, tparker@hollandpartnergroup.com
Holland Project Manager Name & Email: Dane Thiessen, dthiessen@hollandpartnergroup.com
Construction Hours:
- 6:00 am to 6:00 pm non-holiday weekdays
- 8:00 am to 5:00 pm non-holiday weekdays for shoring drilling
- 9:00 am to 6:00 pm weekend/legal holidays
- No work on Sundays.
- It is Holland Construction’s corporate policy to not work on Saturday or Sunday. There will be limited times as required by the City where work will need to occur on a Saturday to accommodate construction traffic such as oversized loads. If Saturday work is required, it will occur between 9:00 am and 6:00 pm.
- Typically, work will not take place on Sundays or any of the following holidays: New Year’s Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and the day after, and Christmas Day.
- If it is required that work be performed at night, outside of standard working hours, on a Sunday or Holiday, then it will be coordinated in advance with City approval and community notification.